In what order does a kitchen remodel happen

The trade that works first decides the trade that works next, and the running record riverside kitchen remodelers sancd holds shows the order never changes. Every kitchen in Riverside, CA moves from demolition through rough work, inspection, closing the walls, cabinets, counters and finish.

Demolition and protection

Elegant modern kitchen featuring white cabinetry and stainless steel appliances.

Cabinets, flooring and any wall being moved come out first. Floors in the rest of the house get covered, and the dust goes out through a window fan or a zip wall. A house near Mount Rubidoux with old paint gets tested before this step.

Rough plumbing and electrical

Bright modern kitchen featuring white cabinets and stainless steel appliances.

With walls open, the plumber runs supply and drain lines, and the electrician sets boxes, runs cable and roughs in the hood duct. Under a house on a raised foundation this is a one day job, and on a slab it includes trenching. Both trades are inspected before anything is covered. Gas lines get a pressure test at this stage as well, and the hood duct is checked for a clear path out of the attic.

Inspection hold point

The rough inspection is the one that cannot be skipped or moved. Booking it a few days ahead keeps the schedule steady, and the walls stay open until the inspector signs the card.

Drywall, floor and paint

Drywall goes up, gets taped and sanded, then primed. Flooring follows if it runs under the cabinets, or comes after if it is a floating floor. In Inland Empire heat, joint compound and paint dry quickly, so crews open windows and run fans to avoid cracking from drying too fast.

Cabinets, counters and backsplash

Upper cabinets are set first, then bases, with a laser line across all of them. The countertop is templated only after the cabinets are fixed in place, and fabrication takes a couple of weeks. Backsplash tile goes on after the counter, and grout cures for a full day before sealing. Heat matters here: grout and adhesive in a warm Riverside kitchen skin over fast, so small batches are mixed and worked in sections.

Lead times and finish

Cabinets and appliances can take weeks to arrive, so they are ordered before demolition. Appliance cutouts are checked against the real dimension sheets, not the showroom. Last come the plumbing fixtures, receptacle covers, hardware, caulk and a final clean, followed by the final inspection that closes the permit near the University of California Riverside and everywhere else in the city.